❌

Normal view

There are new articles available, click to refresh the page.
Yesterday β€” 24 September 2026Main stream

Whatever Happened to the 150,000 Tons of Radioactive Waste Stored Under the Atlantic Ocean?

23 September 2026 at 16:34
More than 200,000 barrels of low-level radioactive waste were stored on the floor of the Atlantic Ocean between 1949 and 1982, reports ScienceAlert. Whatever happened to those barrels? Scientists have descended to the wreckage in a crewed submersible to investigate β€” and found many of the barrels corroded and degraded, their contents spilling across the seafloor. Surprisingly, this isn't necessarily a subversion of the original plan... The International Atomic Energy Agency recommends that low-level waste be disposed of in robust containment in isolation for at least a few hundred years β€” but back in the mid-20th century, the recommendations were a little different. The contemporaneous guidelines recommended that containers needed to reach the seafloor intact and remain sealed only long enough for the short-lived radionuclides to decay. After that, the remaining waste was expected to slowly escape and disperse through the surrounding ocean. Not everything in the barrels would conveniently decay away, however. They contained a radioactive hodgepodge, including cesium-137, plutonium isotopes, and tritium, some of which can persist for thousands of years... [A] few years ago, nuclear engineer Patrick Chardon and marine geologist Javier EscartΓ­n of the French National Center for Scientific Research started to wonder what had become of the dumped waste. That question eventually became NODSSUM β€” Nuclear Ocean Dump Site Survey Monitoring β€” an interdisciplinary project bringing together nuclear physics, geology, oceanography, biology, and marine chemistry to find the barrels and investigate what, if anything, they were doing to the surrounding environment.... [T]he barrels also appeared to function as tiny oases on the otherwise sparsely populated sandy seafloor. Anemones had attached themselves to the barrels. Sponges, sea cucumbers, fish, and crustaceans lived around them, with crabs apparently particularly fond of the artificial shelters... Instruments aboard the ship detected significant signals of cobalt-60 and niobium-94, which the researchers could specifically link to the dumped waste... [Samples are now being analyzed] There is precedent, however, to suggest that even striking levels of radioactivity around a source don't necessarily spread very far. A recent study of the sunken Soviet submarine Komsomolets found radionuclide levels hundreds of thousands of times above background immediately around the leaking reactor β€” but those levels dropped sharply within just a few meters as the material dispersed through the seawater. The NODSSUM team similarly found that, despite the significant radioactive signals around the barrels, activity levels weren't high enough to pose major radiation-protection problems for the scientists handling the samples. [Their three-person submersible] Nautile and the instruments it carried showed no signs of contamination. The real achievement was mapping the exact location of the barrels. "None of this means the waste is harmless," the article concludes β€” but it also doesn't mean we're about to be overrun by radioactive crabs."

Read more of this story at Slashdot.

Before yesterdayMain stream

As Part of California's Coast Begins to Crumble, Is the Clock Ticking on Moving Radioactive Waste?

16 September 2026 at 18:04
"As parts of the Southern California coastline crumbled into the sea, slammed by intense waves and flooding in recent days, oceanographer Kim McCoy had one thing on his mind," reports the Los Angeles Times. He was thinking about "the nuclear waste set in concrete on the beach near San Clemente at the shuttered San Onofre nuclear power plant." "Rising sea levels, storm waves, El NiΓ±o which increases wave height ... these could wash away a section of the walkway that protects the San Onofre seawall, and the waste canisters are just 100 feet away from that," the former wave dynamics researcher and longtime advocate against beach storage of nuclear waste said. Most experts agree the risk of erosion damaging the nuclear waste storage system is extremely low in the near term. The plant's owner, Southern California Edison, has promised the California Coastal Commission to move the waste to higher elevation on-site if modeling shows sea level rise and erosion will start to pose a challenge. But the recent waves, fueled by Hurricane Marie far away in the Pacific, resurfaced the issue of the ultimate fate of the highly radioactive spent fuel that used to power the reactors. "At the moment, it is under control, I think it's essential to say that," said James Day, a geology professor at UC San Diego. "But geologically we must be thinking long term. The waste lasts for hundreds, if not thousands of generations...." [In 2103 some of the site's canisters' approach their intended 100-year lifespans, and the utility may have to start the transfer into new cansiters.] The distinctive twin domes that once housed the reactor cores will start coming down early next year. But the 3.6 million pounds of high-level waste will stay in the coastal community indefinitely. How much of a safety hazard that is depends on whom you ask. "San Onofre is sitting on some fairly young rocks in a seismically active region," Day said at a recent symposium at the Scripps Seaside Forum in La Jolla, hosted by the Samuel Lawrence Foundation. "This is not the sort of place you would leave nuclear waste." Others noted that collapse of beach slopes could make the site more vulnerable to tsunamis. They spoke of the corrosive effects of the ocean air on the steel canisters that hold the waste... Edison says its system will be safe for decades to come. "The maximum credible tsunami here would not even overtake the seawall," said Manuel Camargo, principal manager of decommissioning for Edison, standing on the concrete pad that holds the steel waste storage canisters. "The maximum credible earthquake, somewhere around a 7.0 magnitude, would produce something about half of what this system is designed to withstand...." Edison is bolstering a path below the seawall. Based on state data from the California Ocean Protection Council, the seawall would not be inundated before 2050, Camargo said... Plans for a deep geological repository beneath Yucca Mountain in Nevada crumbled in the face of local opposition in 2011. Utilities around the U.S. now sue the federal government every year to recoup their storage expenses because the Department of Energy has not come through on its promise. The lawsuits cost taxpayers $2 million a day, according to Camargo. "It's so safe that it's almost a problem," Camargo said. "It's not a priority to a lot of folks to move it." "The Trump administration's Department of Energy wants to create 'campuses' in several states to store waste," the article points out, "and, in exchange, give local jurisdictions funding to develop different aspects of the nuclear cycle β€” such as fuel creation, power generation and potentially fuel recycling..." "The administration wants to address the fact that waste is sitting at 80 reactor sites around the country. It also needs places for waste from new reactors it wants to build."

Read more of this story at Slashdot.

Google's Revived Nuclear Power Plant Gets $1.9 Billion Loan From US Government

By: BeauHD
9 September 2026 at 07:00
The U.S. Department of Energy has approved a $1.9 billion loan to NextEra Energy to restart Iowa's shuttered Duane Arnold nuclear plant, which Google has backed as a power source for its growing AI infrastructure. "The sizable loan is the second of its kind, suggesting that the Trump administration views revived nuclear power as a key source of electricity for tech companies seeking to power their AI data centers," notes TechCrunch. From the report: James Danly, Deputy Secretary of Energy, said that the Iowa power plant's restart in 2029 will "drive down electricity costs," though he did not explain how. Just 50 megawatts will be set aside for the local power cooperative, NextEra CEO John Ketchum said during an earnings call (PDF) last year. That capacity would cover 18% of Iowa's demand growth since 2021, the year before ChatGPT was released. Google is reportedly looking to build up to six data centers near the Duane Arnold Energy Center, which hasn't operated since 2020 when an intense rainstorm damaged the power plant. Rather than repair it, NextEra decided to mothball it. At the time, cheap natural gas was flooding the market, making nuclear power economically unappealing. A lot has changed in the last six years, though. After decades of little growth in demand, the sudden rise of AI coupled with broader electrification of the economy meant that utilities and power providers were suddenly scrambling to find new generating sources of electricity. New data centers are expected to nearly triple the sector's electricity demand by 2035.

Read more of this story at Slashdot.

A Man Charged His EV at a Dealership - and Was Billed $418

7 September 2026 at 13:34
The EV blog Electrek reports: A Clinton Township, Michigan man was charged $418 for a single EV charging session at Elder Hyundai's Macomb Township store after finding the charger listed as publicly available on the EVgo app, but didn't discover the charges until after wrapping up his 40-ish minute charging session. "I was flabbergasted," explained Stanley Kpenkann, who had been driving a rented Chevy Bolt EV at the time. "Never in my wildest dreams did I think I would be saddled with a bill of $418 for a charging session." After calling EVgo to report the error, he found that the exorbitant charge wasn't a mistake at all - Elder Hyundai was charging customers an eye-gouging $5 per kWh, plus another $5 for every minute connected. A local news report notes that "After back-and-forth with EVgo, the company processed what it called a goodwill refund of $405." (And the dealership argued their charger was reserved for its own customers and vehicles, so they set prices high to deter outside use.) But Electrek argues the story "speaks to much larger problems among the EV charging business in particular and car dealerships in general..." [In June] Plug & Play EV's Steve Birkett took to LinkedIn to call out his local Hyundai dealer in Union, NJ for charging a ridiculous $15 per kWh to top off his IONIQ 5 (!)... Even worse, he noted that a number of area dealerships that had listed their ports as "public" were actively discouraging public use with signs and stickers designed to turn people away... [U]nlike gas stations, EV charge point operators in many states aren't required to clearly advertise what they'll charge before a driver plugs in in the same way that gas stations are: with clearly legible signage that's visible from the street.

Read more of this story at Slashdot.

Where a Massive Solar Storm Could Take Down the US Power Grid for Millions

6 September 2026 at 19:34
A new study published Friday in AGU Advances "depicts the most advanced picture yet of how a rare but massive solar storm could affect some US industries and electric systems more than others," reports CNN. "During a 250-year solar storm, the East Coast would have widespread potential for grid failure." Researchers modeled what a Carrington Event β€” a 1-in-150-year geomagnetic storm or even rarer β€” could mean for the modern day. They estimate the US economy would lose about $1.5 billion to $2 billion per day from direct and indirect costs, as millions of people face power outages. The findings show the most vulnerable areas are the Northeast and the Northern Plains, especially locations at higher latitudes. No one knows when the next big storm will hit. While the most severe geomagnetic storms are labeled as once-in-a-century or rarer, these events don't follow a fixed schedule. "That timing only averages out on very long timescales," said Anna Kelbert, a geophysicist at the Harvard-Smithsonian Center for Astrophysics, who was not involved in the study but previously studied solar storm effects on power grids. "The event can occur at any time, as soon as a week from now, or centuries later...." [Shawn Dahl, service coordinator at the Space Weather Prediction Center operated by the National Oceanic and Atmospheric Administration in Boulder, Colorado], said the sun is now coming down from a period of heightened activity, which is also when some of the biggest storms to hit Earth have occurred in the past. "We still need a lot of work to be ready...." "We haven't really seen events like this size in the modern era, where we've had all of this high technology and we've had the power grid of this size," said Ed Oughton, researcher at George Mason University and lead author of the new study... Because the US grid's actual structure is proprietary for security reasons, the team used engineering models to create various network and transformer setups including the 10,464 substations and 16,256 transmission lines found across the country... The grid structure also contributes to higher risk in some areas. For instance, the eastern US is linked together in a single grid interconnection. A voltage issue in Maine, if not isolated early, could cascade through the grid to Washington, DC. The West works similarly, whereas the Texas interconnection operates mostly within the state... Power is restored over time depending on any alternative electrical paths that could bypass the substation or availabilities of spare transformers, for instance. "This nationwide analysis shows that we are currently ill-prepared to face a major magnetic storm, and that the societal impacts would be catastrophic," Kelbert said. "The study estimates power disruptions for 5.1 million people and 135,000 businesses," according to the article, and "The outages could last from hours to days to weeks depending on the damage and resources available to get back online, said Oughton."

Read more of this story at Slashdot.

California Lawmakers Greenlight Solar Panels You Can Plug Into the Wall

By: BeauHD
1 September 2026 at 07:00
California lawmakers have passed a bill that would legalize plug-in "balcony" solar systems, allowing residents to connect small solar panels directly to a standard wall outlet after completing a simple online registration. The systems would be capped at 1,200 watts and must meet safety requirements designed to prevent power from feeding back onto the grid during outages. KQED reports: The legislation, SB 868, sailed through the state assembly and senate with bipartisan support. The bill now moves to the governor's desk for signature. The devices can be tented in a backyard, hung off a balcony or placed on a roof. Models range from as low as $300 to $2200, depending on size. The bill would open the solar market to people who were previously left out: renters, people with unsuitable roofs, and those lacking the capital to build out a rooftop system, which can cost in the tens of thousands of dollars. [...] If signed into law by Newsom, the legislation would exempt plug-in solar devices from what critics say is a cumbersome and expensive interconnection application process, and replace registration with a free and straightforward online form. [...] The newly passed bill outlines several device requirements. The balcony solar systems must be capped at generating 1,200 watts per home, plug into a standard outlet, offset a customer's onsite electricity use and meet state and national electrical codes. They also must be certified by an outside safety organization like Underwriters Laboratories and have a feature that would prevent electricity from feeding back into the grid if there's a power outage.

Read more of this story at Slashdot.

Supply Chain Issues Delaying US Grid Batteries' Installation

23 August 2026 at 07:34
Falling prices have made grid-scale storage batteries more attractive, reports Bloomberg. But after decades of stagnant investment, America's grids "are racing to make the upgrades needed to plug them in," with supplies straining for the necessary equipment. Demand for batteries has skyrocketed as electricity use across the U.S. swells, driven by data centers' booming energy needs and increasing electrification. It's also getting harder to get them connected to power grids... As those upgrades get delayed, storage projects are piling up in interconnection queues from coast to coast. For example, Consolidated Edison Inc., a major utility in New York state, says over the last two years the volume of battery storage projects waiting to be connected has grown by 300%... "The whole process of interconnecting these new power plants got really log-jammed and bottlenecked," said Joseph Rand, an energy policy researcher at the Lawrence Berkeley National Laboratory... Nationwide, some 750 gigawatts of energy storage projects β€” roughly equivalent to the generating capacity of more than 700 nuclear reactors β€” are in line to get grid connections, according to the lab's research. Not all of these projects will get built. Many developers already abandoned the queue because of delays. Still, the waiting time is increasing; the median was five years in 2025, up from a year and a half in 2015. The flood of battery projects is expected to continue. Wood Mackenzie, an energy consultancy, projects the U.S. energy storage market will quadruple in the next six years... [Shortages in key equipment] have driven up construction costs and time lines for grid upgrades, leaving utilities struggling to build fast enough. A drought of skilled workers is further slowing them down... In California, PG&E Corp., the state's largest utility, told regulators in January that a key driver of delays was long lead times for specialized equipment. Procuring certain breakers could take nearly four years, according to the utility, which reported a 300% increase in its interconnection workload compared to prior years. In Northern California, for example, holdups to circuit breaker upgrades to a substation in Solano County led to projected delays for two battery projects worth a combined 450 megawatts. Transmission line work in the Bay Area has put another 800 megawatts of energy storage at risk of delay, according to PG&E. Last year New York's Con Ed started requiring developers to help pay for upgrades if their projects will push power demand and strain infrastructure. But that also drew criticism: According to a survey conducted by the trade group New York Battery and Energy Storage Technology Consortium (NY-BEST), the new methodology raised costs by an average of $21 million per project, a 14-fold increase. At least 25 projects have been canceled as a result, according to the group. Battery advocates have appealed to state regulators to get Con Ed to abandon the new policy. Thanks to Slashdot reader Bruce66423 for sharing the news.

Read more of this story at Slashdot.

Solar Power and Batteries Have Been Keeping Europe's Grid Stable

By: BeauHD
18 August 2026 at 03:33
AleRunner writes: "Solar has been doing the 'heavy lifting' to help Europe meet its energy needs amid a string of blistering heatwaves," Euronews tells us. Meanwhile, as Europe's energy demands rise with the heat, jellyfish have been causing shutdowns and reduced power output at multiple reactors at French nuclear plants, as we already discussed. Euronews reports: A new analysis from energy think-tank Ember found that solar output in European countries rose by up to 17 percent on heatwave days in June and July. Researchers say that this helped power the grid as electricity demand increased by as much as a quarter on hot days. Heatwaves often trigger a spike in electricity consumption due to the sudden need for cooling, mainly from energy-intensive air conditioning (A/C) units. The International Energy Agency (IEA) estimates that space cooling, which is mostly A/C units and fans, consumed around seven percent of the world's electricity in 2022. Even in countries where A/C ownership is low, countries experience energy demand spikes when scorching temperatures hit. During the early summer heatwaves of 2025, France, for example, recorded an evening electricity peak that was 25 percent above the off-season average due to air conditioning. Ember's analysis found that during the late-June heatwave this summer, daily electricity demand rose byup to 28 percent in Italy, 23 percent in Hungary, 14 percent in France and 13 percent in Spain compared with pre-heatwave days. It says as heatwave-driven demand increased, solar was the only major power source to perform "better than usual." Compared with other days in June and July, average daily solar generation during the heatwaves was 17 percent higher in France and Hungary, five percent higher in Spain and the same in Italy.

Read more of this story at Slashdot.

US Grid Operator PJM Proposes Forcing Data Center Off Grid During Emergencies

By: BeauHD
17 August 2026 at 15:00
An anonymous reader quotes a report from Reuters: PJM Interconnection, the biggest U.S. grid operator, proposed on Thursday a new framework that would force data centers to use back-up generators when electricity supply on the grid approaches dangerously low levels. The grid operator's proposal dovetails with President Donald Trump's Ratepayer Protection Pledge, a non-binding initiative to protect residential customers from getting saddled with costs related to data center power consumption, PJM said. A new emergency procedure would notify utilities to reduce or transfer the electricity demand from data centers and other large power users ahead of any action that would shut off traditional consumers such as households. PJM said it does not, however, currently have the authority to curtail power to those sites and would require the cooperation of individual state governments. PJM manages the electricity for 67 million people in a territory that stretches from Washington, D.C. to Chicago. Its proposal highlights a growing tension between the rapid expansion of data centers and the ability of the nation's power grid to keep up. If PJM cannot close its supply gap, millions of residents and businesses face an increased risk of blackouts, and the cost of new generation could be passed on to other power consumers. At its recent capacity auction, PJM hit its $325-per-megawatt-day price cap but still came up about 6.8 GW short of its projected reliability needs. With rapidly expanding data centers adding pressure to the grid, PJM has also proposed creating a registry to track their locations and power consumption.

Read more of this story at Slashdot.

How Swarming Jellyfish Overran Three French Nuclear Power Reactors

15 August 2026 at 18:34
A "massive influx" of jellyfish forced Electricite de France SA to shut three units at its Gravelines nuclear power plant this week and reduce output at a fourth, reports Bloomberg. Just as summer temperatures surged, 3.2 gigawatts went offline β€” and the power utility was already facing cuts other nuclear sites as high temperatures reduced the river water available for cooling. More details from ScienceAlert: As Politico reports, the Gravelines nuclear power plant spent hundreds of thousands of euros in 2025 to stop this happening again, only to see a repeat 12 months later... Increasing temperatures in the water can produce more of the plankton and animals that jellyfish feed on, as well as accelerating life cycles and extending breeding seasons.... It's not just jellyfish that have a habit of disrupting human energy infrastructure. Last year in Connecticut, a single raccoon caused more than a thousand power outages, as reported by CT Insider. It's not clear exactly what the raccoon did, but we do know it somehow got into a substation and caused damage to the equipment in there. The unwitting act of sabotage left more than 2,500 customers in the area without power at one stage β€” though repairs were swiftly carried out. Reuters reported Tuesday on how the French utility responded to their jellyfish swarm: EDF has installed fixed cameras at the intake canals and on the filter drum screens to detect any incoming blockages as soon as possible, an engineer told Reuters... The company has also partnered with a French fishing organisation and a sea rescue organisation, which monitor for swarms and can raise an alert to launch targeted trawling operations by fishermen to reduce the swarm's density before it reaches the plant, the engineer said. The fishing boats were deployed [last] Saturday after an initial alarm was raised, limiting the impact from the swarm. The jellyfish that are already on site are being removed with vacuum trucks, he said. No new jellyfish are arriving, so cleanup is finishing, which should lead to a quick restart of the units, they added... Scientists warn such events could become more common due to factors including global warming, the arrival of invasive species, habitat loss of predators and over-fishing. Thanks to Slashdot reader Bruce66423 for sharing the news.

Read more of this story at Slashdot.

America's First Grid-Scale Sodium-Ion Battery Plant Gets Its First Big Test

8 August 2026 at 15:43
"In a milestone for energy storage technology, Peak Energy has selected Sacramento, California, as the home of America's first manufacturing facility dedicated to grid-scale sodium-ion battery systems," according to the sustainability news site Intelligent Living. The move "represents the first large-scale test of whether sodium-ion technology can deliver on its promise of cheaper, safer, and more sustainable grid storage at a scale that actually moves the needle for the U.S. electricity system." The 183,000-square-foot plant, representing a $71 million investment, will produce up to 4 gigawatt-hours of storage annually when production begins in early 2027. That is enough output each year to serve nearly four million homes, and it signals that sodium-ion technology has moved from laboratory promise to commercial reality... Peak Energy, founded in 2023 by former engineers from Tesla, Enovix, and Fluence, announced its Sacramento site selection on July 8, 2026, after a nationwide search that ultimately chose California over Texas... The factory is designed as a system assembly plant rather than a cell fabrication facility. Peak will receive sodium-ion cells, manufactured to its specifications by Chinese suppliers, and assemble them into complete 30-foot-long, 100,000-pound containerized storage systems. Each GS1.1 unit stores 3.1 megawatt-hours, enough to fully charge more than 40 electric vehicles... In the United States, Peak Energy has emerged as the most advanced grid-scale player. It has secured more than 6 GWh of customer commitments, including a landmark deal with Jupiter Power for up to 4.75 GWh through 2030, valued at up to $500 million. Energy Vault has committed to 1.5 GWh of sodium-ion storage for AI data center applications, and RWE Americas has already deployed Peak's first grid-scale system on the MISO grid in Wisconsin, energized in March 2026. General Motors is codeveloping sodium-ion cells with Peak at its Wallace Battery Cell Innovation Center in Michigan, testing 170- and 190-amp-hour cell formats with domestic production targeted for 2028. China, however, remains the global heavyweight. CATL, the world's largest battery manufacturer, unveiled its TENER Sodium energy storage system in June 2026 with a rated cycle life of 15,000 cycles and a projected 25-to-30-year service life. In April 2026, CATL signed a 60 GWh supply agreement with HyperStrong, the largest sodium-ion deal announced to date. BYD, HiNa Battery, and Farasis are also shipping commercial sodium-ion products, including batteries for a $400 electric scooter already on sale in China... Peak Energy's first commercial shipments from Sacramento are slated for the first quarter of 2027, with contracted deliveries to Jupiter Power, Energy Vault, and RWE Americas following shortly after. The company has publicly stated it needs to deploy over $100 million in product in 2026, up from roughly $10 million in 2025, and the Sacramento facility is sized to meet that demand. At the system level, sodium-ion grid storage is already operating. Peak's pilot installation at the SolarTAC testing facility in Watkins, Colorado, stores 3.5 MWh and has been running since 2025. The RWE Americas deployment in Wisconsin, energized in March 2026, marks the first time sodium-ion batteries have backed up the MISO grid, which serves 15 central U.S. states and the Canadian province of Manitoba... According to the International Energy Agency, sodium-ion manufacturing capacity announcements have accelerated sharply since 2024, with global pipelines now exceeding 400 GWh annually... Researchers are also pushing the technology forward. In May 2026, a team at the National University of Singapore published a breakthrough in all-solid-state sodium batteries that could further reduce costs and eliminate the flammable liquid electrolytes found in both lithium-ion and current sodium-ion designs. "The technology's sweet spot is utility-scale, multi-megawatt-hour installations," the article points out, "where the system-level cost savings from passive cooling and longer cycle life outweigh the per-cell energy density penalty..." The article also points out observations from the American Battery Leadership Coalition, an industry group advocating for sodium-ion policy support, that sodium-ion batteries can be built almost entirely from American materials, including coal, sawdust, and agricultural waste. This week Syntropic Power and UNIGRID Inc. also announced "a major partnership to commercialize UNIGRID's proprietary sodium chromium oxide (NaCrO2) battery technology across North America," reports Interesting Engineering, "targeting one gigawatt-hour (1 GWh) of deployments in 2027. The technology could be used in residential, virtual power plant, and large-scale stationary grid applications..." Independent testing by the ISO-accredited Rochester Institute of Technology (RIT) Battery Development Center revealed something surprising. UNIGRID's 210Ah cells displayed endothermic behavior during charging. This means the chemical reaction actually absorbs heat rather than dumping it into the environment. Coupled with a 97.9% cell-level round-trip energy efficiency and remarkable thermal stability under abuse testing, the battery stays cool on its own. The 210Ah sodium-ion cells deliver up to 218Ah of discharge capacity. It demonstrated exceptional durability, retaining over 99% of its capacity after 1,000 full discharge cycles, as well as heat-absorbing behavior during charging. These validated strengths allow Syntropic to optimize its product designs, enabling platforms like GridSpan [its modular DC platform designed for large-scale energy applications with flexible discharge durations ranging from 20 minutes to 20 hours] to operate safely and efficiently at grid scale without needing complex mechanical cooling systems... Commercialization kicks off with Tenet, a safety-focused, wall-mounted system for residential, light-commercial, and virtual power plant uses... Relying on abundant and widely distributed raw materials like sodium and chromium β€” rather than lithium and cobalt β€” protects manufacturers from geopolitical price spikes and material shortages. Apart from offering an alternative to lithium, a successful rollout will demonstrate that the most durable energy storage is the kind that could stay cool entirely on its own. Thanks to Slashdot reader fjo3 for sharing the news.

Read more of this story at Slashdot.

Trump Administration To Pay German Firm $1.2 Billion To Halt US Wind Projects

By: BeauHD
7 August 2026 at 23:30
An anonymous reader quotes a report from the BBC: German energy company RWE has said it will abandon its offshore wind projects in the U.S. after reaching a $1.2 billion payout deal with President Donald Trump's Department of the Interior (DoI). RWE said that it will now reinvest the sum into conventional gas projects, including $900 million in a liquefied natural gas (LNG) export terminal project in Louisiana. "After careful consideration, it was determined there is no path forward to permit these projects in the US for the foreseeable future," the company said in a statement. RWE said it has agreed to relinquish its leases off the California and Louisiana coasts as well as in the New York Bight. Overall, the German firm plans to invest approximately $19.6 billion in the U.S. over the next six years "to grow its generation capacity." Interior Secretary Doug Burgum said in a statement posted on X that Americans deserve an energy system built on common sense and not one dependent on "costly subsidies." "We welcome RWE's agreement and voluntary investment in projects that strengthen our nation's energy security," he added. Earlier this year, the DOL reached a deal with TotalEnergies putting an end to the French company's offshore wind projects in the U.S. "Instead, the firm agreed to reroute investment to build a LNG plant in Texas and to develop 'upstream conventional oil' in the Gulf of Mexico," reports the BBC. Another similar deal was signed with Charlotte-based Duke Energy last month to terminate the company's offshore wind lease in the Carolina Long Bay area.

Read more of this story at Slashdot.

Texas Halts Data Center Connections To Power Grid Amid Overwhelming Demand

By: BeauHD
4 August 2026 at 23:30
An anonymous reader quotes a report from Ars Technica: Nowhere is the US data center boom bigger than in Texas. But less than a year after declaring Texas the "epicenter of AI development," Governor Greg Abbott has declared a moratorium on all new power grid connections for data centers -- at least until developers provide more information about their projects' potential impacts on the grid and communities. The Republican governor directed regulators in an August 3 announcement at the Public Utility Commission of Texas and the grid operators at the Electric Reliability Council of Texas (ERCOT) to perform a "comprehensive verification and audit of all data centers advancing through ERCOT's interconnection process." As an independent system operator, ERCOT oversees a power grid that operates separately from the rest of the United States and provides services to most of Texas. Texas has aggressively courted data center development with its availability of cheap land and relatively abundant energy resources, along with offering state incentives, like tax breaks and fewer regulations. That puts the state on track to surpass Virginia in becoming the largest US data center market. But the recent AI boom and the accompanying frenzy of data center development threaten to overwhelm the Texas grid on paper, despite the state leading the country in adding new power generation. The ERCOT interconnection queue currently includes more than 1,800 projects representing over 474 gigawatts' worth of requests to connect to the Texas grid -- more than five times Texas' record peak electricity demand -- and about 90 percent of those power connection requests come from data centers. "That unprecedented load growth could endanger the reliability and stability of the Texas electric grid," according to the statement from Abbott's office. Many of those data center projects may never materialize for various reasons. But ERCOT has still forecast that data center demand and other factors could drive statewide electricity demand to double the current demand record by 2032, according to The Texas Tribune. The review will examine each project's projected electricity consumption, reliance on the grid and state incentives, ownership, and water use. It will also assess measures intended to "reduce impacts on neighboring property owners and communities," including noise controls, lighting, traffic improvements, setbacks, and emergency planning. Ars Technica notes that the directive does not address air pollution or greenhouse-gas emissions and does not apply to data centers generating their own power on-site.

Read more of this story at Slashdot.

NextEra, Brookfield to Build $100 Billion Kentucky Data Campus

By: BeauHD
29 July 2026 at 16:00
NextEra and Brookfield plan to invest more than $100 billion to transform a former uranium-enrichment site in Kentucky into a data center campus with a generating plant. "The privately funded effort will include construction of 2 gigawatts of natural gas-fired power at or near the site in Paducah in western Kentucky, and as much as 2.6 gigawatts of battery storage capacity," reports Bloomberg. " For context, a single gigawatt of capacity is roughly the output of a traditional nuclear power plant and can power about 750,000 homes at any given moment." From the report: Brookfield will develop and operate the 1.8 GW data center campus, which will occupy portions of the sprawling 3,556-acre Energy Department site once used to produce weapons-grade uranium and fuel for nuclear reactors. Operations using the now obsolete enrichment technology known as gaseous diffusion stopped in 2013 and the site is now subject to cleanup efforts. Construction is expected to be completed in 2031, the Energy Department said. "The U.S. government is leveraging its assets -- like our federal lands -- to add power generation, create jobs, and ensure the United States wins the AI race," Energy Secretary Chris Wright said in a statement. The project is expected to create 8,000 construction jobs and 600 permanent positions, the department said.

Read more of this story at Slashdot.

❌
❌